refund
frames
refund.XX:
refund.XX sub-ARG0 obj-ARG1
- The Illinois Supreme Court ordered [ARG0 the commission] *-1 to audit Commonwealth Edison 's construction expenses and [rel refund] [ARG1 any unreasonable expenses] .
- [ARGM-TMP Last year] [ARG0 Commonwealth Edison] had *-1 to [rel refund] [ARG1 $ 72.7 million *U*] [ARGM-PNC for poor performance of its LaSalle I nuclear plant] .
refund.XX sub-ARG0 NP-ARG2-to obj-ARG1
- [ARG0 Commonwealth Edison Co.] was ordered *-1 *-2 to [rel refund] [ARG1 about $ 250 million *U*] to [ARG2-to its current and former ratepayers] [ARGM-PRP for illegal rates collected * for cost overruns on a nuclear power plant] .
- [ARG0 The network] [ARGM-MOD must] [rel refund] [ARG1 money] to [ARG2-to the advertisers] and loses considerable revenue and prestige .
refund.XX obj-ARG1
- In August , the commission ruled that [ARG1 between $ 190 million and $ 195 million *U* of the plant 's construction cost] was unreasonable and [ARGM-MOD should] be [rel refunded] *-1 , [ARGM-MNR plus interest] .